Given the following activities, what is the project duration? A: no predecessor, 4 days; B: no predecessor, 5 days; C: no predecessor, 3 days; D: predecessor C, 7 days; E: predecessors A, B and D, 5 days.
Engineering Professional Practice / Project Planning and Scheduling