Home›Question bank›PANA Academy - project-planning - Reviewed subset 2026-09NEC Common · 2083 · Question 15A schedule performance index (SPI) of 0.76 means:Engineering Professional Practice / Project Planning and SchedulingAYou are over budgetBYou are ahead of scheduleCYou are only progressing at 76 percent of the rate originally plannedDYou are only progressing at 24 percent of the rate originally plannedChecking answer access…